Part   2  Highlights of 2015-2017             Town Planning Board Report 2015 - 2017  21






                                   Railway Property Development




                                   As announced in the 2016 Policy Address, the Government has been actively
                                   exploring the development potential of stations and related sites along existing and
                                   new railway lines to make optimal use of such land.
                                   Kam Sheung Road Station and Pat Heung Maintenance Depot

                                   To take forward the planning for residential development at the two West Rail
                                   sites at Kam Sheung Road Station and Pat Heung Maintenance Depot with a view
                                   to increasing the supply of housing land, proposed amendments to the approved
                                   Kam Tin South OZP No. S/YL-KTS/11 were agreed by the Board on 8 May 2015.
                                   The two West Rail sites were rezoned to “Other Specified Uses” (“OU”) annotated
                                   “Railway Station and Public Transport Interchange with Commercial/Residential
                                   Development” and “OU” annotated “Railway Depot with Commercial/Residential
                                   Development” zones respectively. It was estimated that the two sites would provide
                                   about 8,752 flats with a population of about 21,400. The proposed amendments of
                                   the two West Rail sites were exhibited for public inspection on 29 May 2015.  After
                                   giving consideration to the 55 representations and 330 comments, the Board on 11
                                   March 2016 decided not to uphold the representations. The draft OZP was approved
                                   by the CE in C on 30 August 2016 and renumbered as S/YL-KTS/13.




















                                   Pat Heung Maintenance Depot Conceptual Scheme Plan






























                                   Kam Sheung Road Station Conceptual Scheme Plan