Pak Shing Kok Ventilation Building
The site is located at Chiu Shun Road and about 400m away from the MTR Hang Hau Station. The
major part of the site is used for the Pak Shing Kok Ventilation Building by the MTR Corporation
Limited (MTRCL) and the rest are man-made slopes on government land. To optimise the
development potential of the site, the Board agreed on 29 May 2020 to rezone the site from an
area shown as ‘MTR Pak Shing Kok Ventilation Building’ and zoned as “GB” to “R(A)8” for private
residential development subject to a maximum plot ratio of 6 and a maximum building height of
130mPD. Two residential towers were proposed on top of the existing ventilation building without
affecting its operation, providing about 432 flats.
The draft Tseung Kwan O OZP No. S/TKO/27, incorporating the amendments amongst others, was
exhibited for public inspection under section 5 of the Ordinance on 19 June 2020. After giving
consideration to the 130 representations and 6 comments, the Board on 19 February 2021 decided
not to propose any amendment to the draft OZP. The draft OZP was approved by the CE in C on 1
June 2021 and renumbered as S/TKO/28.
Site rezoned to “R(A)”8
Conceptual Development Plan (Indicative Only)